Real-time contingency analysis shows that a transmission line will overload for the loss of Line X. What is the best course of action for the Transmission Operator?

Prepare for the NERC Health and Safety Institute Test. Study effectively with flashcards and multiple-choice questions, each with hints and explanations. Excel in your exam!

The best choice in this situation is to be prepared to shed load if Line X trips. This approach allows the Transmission Operator to take proactive measures to maintain system reliability without immediately disrupting service. Real-time contingency analysis is an important tool that helps predict potential overloads and other issues that could arise from the loss of a critical line, like Line X. By being prepared to shed load, the operator can quickly mitigate the risk of overload, ensuring that the system remains stable.

This option emphasizes preparedness and proactive management of transmission system reliability. In the event of an actual trip of Line X, having a plan in place to shed load can prevent cascading failures or major outages.

The other choices may seem viable at first glance but do not prioritize the appropriate level of readiness or could lead to unnecessary disruptions. For instance, opening the line may cause further instability or disruption of service and typically would not be an immediate response to a potential overload scenario. Redispatching generation can be a response but may not be sufficient on its own if the situation is urgent or if there are constraints in generation capacity. Shedding load immediately could lead to unnecessary service interruptions and consumer dissatisfaction without assessing the situation carefully. Thus, the best course of action focuses on advance preparation to ensure reliability without